New Projects, Expansions &

Diversifications

 

 

  

Petrochemicals

Indian Oil Corp Ltd

3079/3, JB Tito Marg, Sadiq Nagar,

New Delhi - 110049 Tel: 011-26260000

Project: To set up a petrochemical hub for downstream industries at Panipat in two phases

Cost: Rs 37,300 million

Status: Phase I is expected to be completed by 2012 and phase II by 2016.

 

Hindustan Mittal Energy Ltd

Inox Towers, Sector 16 A, Plot No.17,

Noida, UP - 201301 Tel: 0120-4634500

Fax: 0120-4271940 Email: info@hmel.in

Project 1: To implement a petroleum complex at Guru Gobind Singh Refinery, Bathinda, Punjab

Cost: Rs 1,783.3 million

Status: To be executed in 15 months

 

Chemicals

Chemcrux Enterprises Ltd

T-7, National Plaza, R C Dutt Rd, Vadodara,

Gujarat - 390007 Tel: 0265-2344803/2358903

Fax: 0265-2332910

Project: To set up a chlorobenzoic acid unit with a capacity of 2,500 tpa

Location: Ankleshwar, Bharuch, Gujarat.

Cost: Rs 30 crore

Status: Completion expected in Dec 2010.

 

Galaxy Surfactants Ltd

C-49/2, TTC Indl Area, Pawne, Navi Mumbai - 400703 Tel: 022-27616666/65134444 Fax: 022-27615883

Email: galaxy@galaxysurfactants.com

Project: To set up an organic surfactants unit

Location: Jhagadia, Bharuch, Gujarat.

Cost: Rs146 crore

Status: Completion by Nov 2010

 

Fertilisers

Nagarjuna Fertilisers & Chemicals Ltd

Nagarjuna Rd, Kakinada, A P - 533003

Tel: 0884-2360390/391 Fax: 2362084

Project: To implement revampling of its Kakinada facillity

Cost: Rs 1,100 million

Status: Expected to be completed by Oct 2009

 

Tata Chemicals Ltd

Bombay House, 24 Homi Mody St, Fort,

Mumbai - 400001 Tel: 022-66658282 Fax: 66658143

Project: To enhance capacity for ammonia plant (1,520 tpd to 2,000 tpd) and urea plant (2,620 tpd to 3,500 tpd)

Location: Babrala plant, Budaun, UP

Cost: Rs 2,080 milllion

Status: Recently commissioned

Pipelines

Gail India Ltd

16, Bhikaji Cama Place, New Delhi - 110066

Tel: 011-26172580/26182955 Fax: 26185941

Project 1: To implement a natural gas pipeline project in the northern region to cover 610 kms Dadri-Bawana-Nangal.

Cost: Rs 25,000 million

Status: Preliminary stage

 

Project 2: To lay a similar 1,400 kms Jagdishpur-Haldia pipeline for Barauni Plang in Bihar

Cost: Rs 70,000 million

Status: Planning stage.

 

Drugs & Pharmaceuticals

AKR Life Sciences Ltd

Krushna 2-C, Arun Society, Mahalaxmi Char Rasta,

Ahmedabad, Gujarat.

Project: To set up a bulk drugs unit

Location: Ahmedabad, Gujarat

Cost: Rs 150 crore

Status: Completion scheduled by January 2011

 

Aurobindo Pharma Ltd

Plot No.2. Maitri Vihar, Ameerpet,

Hyderabad, A P - 500038 Tel: 040-66725000

Fax: 23741080 Email: info@aurobindo.com

Project: Drug formulations unit to manufacture tablets & capsules Location: Jedcherla, AP

Cost: Rs 2,000 million

Status: Recently commissioned

 

Faluck International

B, 3 Jabuka Avenue, Ahmedabad, Gujarat - 382350

Tele/fax: 079-22704025

Email: faluckint@gmail.com

Project: To set up a 525 tpm integrated pharmaceutical manufacturing unit.

Location: Ahmedabad, Gujarat

Cost: Rs 30 million

Status: Project scheduled to be completed by June/July 2009.

 

Plant & Equipment

L&T MHI Boilers Ltd

L&T House, Ballard Estate, P O Box : 278,

Mumbai - 400001 Tel: 022-67525656 Fax: 67525893

Email: ccd@lth.ltindia.com

Project: To implement a heavy duty boilers manufacturing unit (4,000MW)

Location: Batha, Surat, Gujarat

Status: Scheduled for completion by the end of 2009.

 

Biotechnology

Southern Online Biotechnologies Ltd

No.A3, 3rd Floor, Office Block Samrat Complex,

Saifabad, Hyderabad, AP - 500004

Tel: 0181-2722060/2723160 Fax: 2722931

Project: To set up a bio-diesel manufacturing unit (250 tpd)

Location: Duppituru, Visakhapatnam, AP.

Cost: Rs 900 million

Status: Slated for completion by June 2009.

 

Fermentation

J C Biotech Pvt Ltd

Plot No.3, Sagar Society Rd No.2, Banjara Hills,

Hyderabad, AP - 500034 Tel: 040-23540616

Fax: 23540544

Email: info@jcbiotec.com

Project: To set up a chemical fermentation unit

Location: Ongole, AP.

Status: Slated completion by Feb 2010.